Sealing of main supply lines at Augsburg University Hospital
CABLE ENTRY WITH STAINLESS STEEL FLANGE HRD2X150-1X80
Augsburg
CABLE ENTRY WITH STAINLESS STEEL FLANGE HRD2X150-1X80
EALING OF MAIN SUPPLY LINES AT AUGSBURG UNIVERSITY HOSPITAL
EALING OF MAIN SUPPLY LINES AT AUGSBURG UNIVERSITY HOSPITAL
Project Description
The project involved the Anbau West annexe, an intensive care centre with institutes for microbiology and laboratory medicine, hemostasiology, transfusion medicine and pathology. The six-storey building contains a total floor area of approx. 30,000 square metres, with an effective area of 12,900 square metres. The planned investment amounts to approx. 110 million euros. The State of Bavaria will cover 90% of this cost with the remaining 10% from former management, the city and the district of Augsburg. Work began at the end of 2013 and is set to finish in October 2020
Cable entry into the media channel
The existing main supply lines could not be rerouted during construction of an accessible service duct. A recess around the cables was left open during the construction work. Image: Cable entry into the service duct.
Cable exit from the media duct
Special feature: Cables enter in and out of the service duct at varying angles. The position of the cables can not be altered. Image: Cable outlet on the service duct.
Close-up: Cable entry into the service duct
Close-up: Cable outlet on the service duct
Cable entry into the media channel
Solution: Overmeasure of a protrusion flange in split-design with different pipe socket outlets in relation to the exit angle of the cable. Image: Cable entry into the service duct.